Copper Mountain Mine

Annual Operating Statistics

Production Guidance

    2023E
Copper (Mlbs)   88 to 98

Annual Operating Statistics

Mine Production Information
Copper Mountain Mine (100% Basis)
2022 2021 2020
Mine
Total tonnes mined (000’s)1 52,755 56,897 55,045
Ore tonnes mined (000’s) 12,937 13,358 14,173
Waste tonnes (000’s) 39,818 43,540 40,872
Stripping ratio 3.08 3.26 2.88
Mill
Tonnes milled (000’s) 12,707 13,406 14,336
Feed Grade (Cu%) 0.24% 0.38% 0.32%
Recovery (%) 79.1 79.8 78.0
Operating time (%) 85.4% 91.9% 92.4%
Tonnes per Day (TPD) 34,814 36,729 39,169
Production
Copper production (000’s lbs) 52,902 90,140 77,551
Gold production (oz) 21,771 28,736 29,227
Silver production (oz) 247,291 523,821 392,494
C1 cash costs per pound of copper produced (US$) $3.53 $1.49 $1.43
All-in-sustaining cost per pound of copper produced (US$) $4.20 $1.84 $1.58
All-in cost per pounds of copper produced (US$) $4.78 $2.12 $1.90

1. Excludes ore re-handle from stockpile